Power supply is crucial at any construction site. Whether you’re building a home, villa, or commercial project, getting a BESCOM connection for construction is vital for safely operating equipment and lighting.
This guide outlines the step-by-step process to obtain a BESCOM electricity connection in Bengaluru. It covers the required documents, fees, and tips to avoid delays.
Table of Contents
ToggleBESCOM (Bangalore Electricity Supply Company Limited) provides electricity distribution in Bengaluru and nearby areas. For construction, BESCOM offers two connection types:
Every construction project should begin with a temporary connection, which can be converted to a permanent supply once the building is ready.
You’ll need:
You can apply:
Submit the application form with your documents and load details. You’ll receive an acknowledgement number to track your application.
A BESCOM engineer will visit your site to check:
After the inspection, you’ll receive a quotation for connection charges and a security deposit.
Once you receive the quotation, pay the deposit and service charges online or at the BESCOM office. Charges depend on:
Typically, small residential sites need 3–5 kW, with initial charges ranging from ₹8,000 to ₹20,000.
After payment, BESCOM installs:
You’ll receive a temporary electricity connection valid for 6 months to 1 year, extendable upon request.
Once construction is complete and you have the Occupancy Certificate (OC) or Completion Certificate, apply for a permanent BESCOM connection. Required Documents:
After inspection, BESCOM will disconnect the temporary line and install a permanent meter for domestic or commercial use.
Delays often occur due to incomplete documents or pending inspections.
At EcoPro Builders Private Limited, we assist homeowners with BESCOM, BBMP, and BWSSB approvals — managing all permits for smooth and lawful home construction in Bengaluru.
📞 Call: +91 9632196909
🌐 Website: www.ecoprobuilders..in
📍 Services: BESCOM & BBMP Approvals | Home Construction | Project Management
A BESCOM temporary connection provides electricity to a construction site for a short period, typically 6 months to 1 year. It allows the use of electrical tools, machinery, and lighting during home or building construction. Once the project is complete, the temporary connection is converted into a permanent domestic or commercial connection.
The following documents are needed for applying for a BESCOM connection:
Ownership proof (Sale Deed / Khata Certificate)
Building plan approval from BBMP or BDA
Latest property tax receipt
Address proof and ID of the owner
Electrical contractor’s license copy
Load requirement and wiring diagram
Completion certificate from a licensed electrical contractor
You can apply:
Online: via the BESCOM website → Online Services → New Connection
Offline: at your nearest BESCOM subdivision office.
After submitting your documents and load details, a BESCOM engineer will inspect your site before issuing the connection approval.
It usually takes 7 to 15 working days to get a temporary construction connection, and 15 to 30 days for a permanent connection after receiving the Occupancy Certificate. Timelines depend on document accuracy and inspection schedules.
Charges vary based on your power load requirement and distance from the supply point.
For small residential construction sites, the initial cost is typically ₹8,000 to ₹20,000, which includes the security deposit, meter cost, and service line installation charges.
Yes, BESCOM offers an online application facility through its official website. You can fill out the new connection form, upload all documents, pay the required fees, and track your application status online.
Temporary connection: Given for construction purposes, valid for a limited time.
Permanent connection: Issued after construction completion and receipt of the Occupancy Certificate (OC).
The temporary connection can be converted to permanent once the project is ready for occupancy.
Using electricity illegally or without an authorized BESCOM connection is a punishable offense under the Electricity Act. BESCOM can impose penalties, disconnect supply, or file legal action. Always obtain an official connection for safe and lawful power use.
You can hire a licensed electrical contractor or consultant to handle your BESCOM application, documentation, and inspection.
At EcoPro Builders Private Limited, we assist homeowners and builders with BESCOM, BBMP, and BWSSB approvals, ensuring a hassle-free start to your construction project.
Visit the BESCOM Online Portal → Consumer Services → Application Status.
Enter your application number to view your approval progress and engineer assignment details.